Last night, I started a test to see if I could get non-hosted videos on this blog. Unfortunately, I have to upgrade packages to do so and I know that this is not the final home of this blog, so I am not going to invest in that at the moment.

In lieu of doing something new, I will summarize where I am at on this current project. I am in the punchlist phase. That means that I am essentially done with my work in the apartment minus a few things here and there. I still need to

  • Hang a ceiling fan
  • Install some window film to obscure direct view – waiting for delivery
  • Build a face frame for the microwave cabinet
  • Oversee cabinet painting and final ceiling touch-up – waiting for paint
  • sub floor patching
  • Install the baseboard molding – waiting for floor
  • Move in and install the appliances – waiting for floor

As you can see, the bathroom is a long way from being done. I would estimate two weeks of solid work. I will be doing the roofing when the framing is done. And I am waiting for the framing to be done so I can finish the siding and painting.